Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Belgium - National holidays
Belgium - Long-lead equipment (LLE) and Supply Chain narrative
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Spain - Labour costs
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Long-lead equipment (LLE) lead times have changed drastically since the start of 2022. Suppliers have seen the implications of material shortages, delays and price hikes throughout the supply chain, which is leading to extended lead times and reduced commitment from suppliers for new projects. The key areas in focus are:
Related Insights
22 August 2023
Linesight Global Commodity Report - Q2 2023
22 August 2023
Linesight European Commodity Reports - Q2 2023
22 August 2023
Linesight Ireland Commodity Report - Q2 2023
22 August 2023
Linesight UK Commodity Report - Q2 2023
22 August 2023
Linesight Sweden Commodity Report - Q2 2023
22 August 2023
Linesight Germany Commodity Report - Q2 2023
22 August 2023
Linesight Switzerland Commodity Report - Q2 2023
22 August 2023
Linesight Netherlands Commodity Report - Q2 2023